1/3
CRL C8 Otahuhu Station Works

Client: CRL

Contract Value: $7,500,000 

Project Duration: 9 Months

Completed: 1/21

 

Libbet have recently been awarded the Contract to ​deliver the Civil and Building scope for the works required to commission a new third platform and new staff accommodation building at the Otahuhu Station.

 

The works include the following:

 

  • Installation of OLE canopy masts

  • Complete platform fit-out (canopies, lighting, seating, bins, signage, CCTV, help points, ticketing, gates and fencing)

  • Construct new staff accommodation facilities 

  • Construct new pedestrian overbridge to connect the existing island platform and third platform