1/2
Penrose Platform 3 Extension

Client: Auckland Transport

Contract Value: $900,000

Project Duration: 6 Weeks

Completed: 4/18

 

Libbet undertook a project to extend the length of the Penrose Station 3rd Platform so six car trains could be used during special events at Mount Smart Stadium. 

 

This fast tracked development was a particularly challenging project. The construction techniques we employed sought to maximise the construction activities within an ultra-fast track timeframe. Round the clock shifts meant we were able to deliver this extension in a six week timeframe, to coincide with the 2018 Ed Sheeran concerts.